New Detached ADU in Martinez: What the Project Actually Involves
A detached ADU in Martinez runs $90,000 – $220,000 for a ground-up unit, and most take 8 – 12 months from the first site visit to the day you hand over keys, with roughly 4 – 6 of those months spent in design and permitting before a shovel turns. If you’re pricing a larger scope that folds an ADU into a bigger build, our Home Additions & ADU in Martinez page covers the wider project. To put real numbers on your lot, call (855) 471-4163 and we’ll set a free on-site estimate.
How We Build a New Detached ADU, Stage by Stage

Every lot is different, but the sequence doesn’t change much. Here’s what actually happens, and where you make the calls that matter.
Stage 1: Site visit and feasibility (week 1)
We walk the parcel with you and look at access, slope, drainage, and where utilities enter. On Martinez hillside streets, this is where we find out whether the site needs grading or a retaining solution before anything else proceeds. You decide the unit size and placement at this stage. Most homeowners settle on 500 – 800 square feet.
Stage 2: Design and permitting (months 1 – 6)
This is the long pole. Drawings get drafted, structural and energy calcs get run, and plans go to the city for plan check. You’ll sign off on layout and finishes here. We handle the submittal and the back-and-forth. Expect at least one round of plan-check comments; that’s normal, not a red flag.
Stage 3: Site prep and foundation (weeks 1 – 4 of construction)
Grading, excavation, footing, and slab. Access matters in the downtown grid, where older tight-lot parcels can mean equipment has to come through a narrow side yard. You don’t make decisions here; you mostly watch progress and confirm the schedule.
Stage 4: Framing, rough-in, and envelope (weeks 5 – 14)
Walls go up, roof gets dried in, and plumbing, electrical, and HVAC get roughed in before inspections. On the older parts of Martinez, this is also where we tie the new structure’s utilities back to the main house, and where wind-driven rain off the strait can push exterior scheduling. You pick fixtures and confirm rough-in locations in this window.
Stage 5: Finishes, final inspection, and handoff (weeks 15 – 20)
Insulation, drywall, cabinets, flooring, paint, and final inspections. Once the city signs off, we do a walkthrough with you and hand over keys. The whole job is backed by our 730-Day Done Right Promise.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
What You’ll Choose Between for Your ADU
The build quality and your budget mostly come down to a handful of choices. Here’s the honest trade-off on each.
- Foundation type: slab-on-grade is the simplest and cheapest on flat lots; a raised or pier foundation costs more but suits sloped Martinez hillside sites and handles drainage better.
- Roofing: architectural asphalt shingles from Owens Corning or IKO are the value pick and hold up well against the strait’s wind and rain; standing-seam metal costs more but lasts longer and shrugs off wind better.
- Utilities: tying into the main house is often cheaper than running separate service, but a separate meter can make sense if the ADU will be a rental. Worth running the numbers with us.
- Insulation and windows: better insulation and impact-rated or dual-pane windows cost more up front and pay back in energy bills; a big factor given afternoon wind and swingy Delta temperatures.
- Finishes: a full kitchenette and tile shower cost more than a kitchenette-less studio; decide how independent the unit needs to be.
What a New Detached ADU Costs in Martinez, CA

The $90,000 – $220,000 range reflects real variables, not vague “it depends.” Here’s what pushes it toward one end or the other.
- Size: a 500-square-foot studio sits near the low end; an 800+ square-foot one-bedroom with full kitchen and bath nears the top.
- Site conditions: flat and ready is cheap; sloped, poorly draining, or access-constrained hillside lots add grading, retaining, and equipment hassle.
- Utility tie-ins: a short tie-back to the main house costs far less than new service runs.
- Finish grade: builder-grade vs. custom cabinets and tile swing the number substantially.
- Permit scope: a straightforward plan-check is cheaper than one with structural or hillside complications.
A written estimate covers design, plans, permits, foundation, framing, envelope, utilities, and finishes, with a line-item breakdown. What it typically doesn’t cover is unexpected site work like discovering a failing retaining wall or buried utilities, which we’ll flag as soon as we find it. Upfront pricing, no surprises. Call (855) 471-4163 for a free estimate.
See the difference
Before
After
Before
After
Before
AfterWhat Martinez Homes Specifically Do to This Job
Martinez sits on the Carquinez Strait where the Bay meets the Delta, and that shapes an ADU build here in ways a generic plan misses. Salt air and wind-driven rain off the water mean we spec exterior materials and fasteners for corrosion and weather resistance, and we plan roof and exterior work around the strong afternoon winds that funnel through the strait and the wet winter storm windows. On the hillside streets above downtown and out toward Alhambra Valley, slope drainage and retaining-wall integrity are a live question, and a heavy winter rain can expose a problem you’d rather catch before framing goes up. Downtown, in the older blocks off Main Street, tight-lot parcels and century-old structures mean abatement and careful utility tie-ins are common scopes. We cover all of Martinez and the surrounding area with Home Additions & ADU work. Homeowners often pair this with Concrete Driveways & Concrete Work in Martinez or Paver Driveways in Martinez to give the new unit its own parking and path.
Serving Martinez, CA – Our Local Coverage Area
We serve Martinez and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Martinez

Most run 8 to 12 months total, with 4 to 6 months of that in design and permitting and 4 to 6 months of construction. Call (855) 471-4163 for a timeline on your lot.
Yes. A ground-up detached unit requires a building permit with plan review, and we handle the submittal and plan-check process for you. Call us to talk through what your parcel will need.
Plan for $90,000 to $220,000, driven mostly by size, site conditions, and finish grade. Call (855) 471-4163 for an exact quote, free on site.
Often yes, though sloped hillside sites and tight downtown parcels need extra grading, retaining, or access planning. We’ll assess your lot and tell you what’s realistic.
Every project carries our 730-Day Done Right Promise: if it’s not done right, we make it right. Call to hear the details.
Get a Free Estimate for Your New Detached ADU in Martinez
We’ll walk your lot, talk through size, site, and utilities, and give you a written, line-item estimate for a new detached ADU, with financing options including 0% for 18 months and $1,000 off projects over $10,000. No pressure, no vague numbers. Call (855) 471-4163 to set up your free estimate.
Written by the team at Groundwork Construction Co.